Estimates

  • Code cleaning (2 days)
    • Basic code cleaning : 1 day
    • Implement constructors/destructors and link classes together : 1 day
  • Constants (1 day)
    • Implement constants / exceptions : 1 day
  • SLP (4 days)
    • Headers : 1 day
    • Body : 2 days
    • Test : 1 day
  • Transport (6 days)
    • Write transport manager : 1 day
    • Switchboard : 1 day
    • Direct connection support : 1 day
    • TLP : 1 day
    • Test : 1 day
    • UUX Notification (?) : 1 day
  • Session (4 days)
    • Session manager : 1 day
    • Session : 2 days
    • Test : 1 day
  • Misc (5 days)
    • File transfer support : 4 days
    • Support for winks and voice clips : 1 day
  • Webcam (3 days)
    • Webcam session : 1 day
    • The rest : 1 day
    • Test: 1 day
  • MSNObject (1 day)
    • MSNObject stuff : 1 day
  • Test it all together : 3 days
  • Clean up snit objects : 1 day

Total : 30 days

Roadmap

  • Basic code cleaning : 1 day DONE
  • Implement constructors/destructors and link classes together : 1 day DONE
  • Implement constants / exceptions : 1 day DONE
  • Write transport manager : 1 day DONE
  • Switchboard : 1 day DONE
  • SLP headers: 1 day DONE
  • SLP body: 2 days DONE
  • TLP : 1 day DONE
  • Session manager : 1 day DONE
  • Session : 2 days DONE
  • MSNObject stuff : 1 day DONE
  • Tests: 3 days DONE
  • File transfer support: 4 days DONE
  • Webcam session : 1 day DONE
  • Webcam - the rest : 1 day DONE
  • Test: 1 day DONE
  • Direct connection support: 1 day DONE
  • Support for winks and voice clips : 1 day DONE
  • Test it all together : 3 days DONE
  • Clean up snit objects : 1 day DONE
  • UUX Notification support (?) : 1 day

Bugs related to MPOP and p2pv2

  • Add them here